[ARCHIVED] Edgewater Park Township & Beverly City

Project Name:Cooper Street (CR 630)
Start Date: 9/9/2021
End Date: 9/24/2021

Project Type:  Burlington County

Description:  The project involves pavement milling and overlay of Cooper Street (CR 630) from Route 130 in Edgewater Park Township to County Route 543 in Beverly City. The work is expected to take about two weeks to complete.

Limits:  From Route 130 in Edgewater Park Township to County Route 543 in Beverly City.

Impact:  Traffic will be maintained during milling and paving operation. Motorists using the roadway may experience delay and are recommended to find alternative routes during the work.

Contractor:  Earle Asphalt Co., Inc., of Farmingdale, NJ